AIR ITAM
Tuan Pavilion
Tuan Pavilion, a high-rise residential development spanning 2.4 acres along Solok Zoo 1 in Air Itam, conveniently located near the Permata Sports Complex. Situated less than 2km from Sunshine Central Mall, it offers easy access to the upcoming Air Itam Bypass, scheduled for completion in 2025. This project consisting of two ... Read More
Temporary road closure for beam launching works along Lebuhraya Thean Teik
In light of the ongoing Air-Itam Bypass project, another temporary road closure is scheduled to take place from the 3rd to the 4th of May 2024, between the hours of 9pm and 5am. This closure is necessary to facilitate beam launching works along the Lebuhraya Thean Teik, specifically between Desa ... Read More
Ayer Itam – Tun Dr LCE Expressway bypass on track for completion by January 2025
The construction of Bandar Baru Air Itam to Tun Dr Lim Chong Eu Expressway (Package Two) bypass is now at 35.14%. Project director Nasfiza Mokhtar, who was from the Public Works Department and currently with Penang Infrastructure Corporation (PIC), said the project was behind schedule by about 2%. She said, however, ... Read More
Ayer Itam – Tun Dr LCE Expressway bypass now 33% completed
In an update provided by the State Infrastructure and Transport Committee Chairman, Zairil Khir Johari, the construction of the Ayer Itam-Lebuhraya Tun Dr Lim Chong Eu bypass (Package Two) in Penang is progressing well. As reported by TheStar newspaper, the project is currently at 33% completion, with an expected finish ... Read More
Weekly Newsletter
Latest Projects
TODAY'S MOST READ
RECENT COMMENTS
- @santokh We shouldn't say cheap. It's a good addition to Bayan mutiara area. The design...Bin on SITE PROGRESS: The Pier (Nov 2026)
- my gosh! why does it look so "cheap"?? ...santokh on SITE PROGRESS: The Pier (Nov 2026)
- @lawrence The flying over currently build near the TNB is the U turn for traffic...Bin on Air Itam–Tun Dr LCE Expressway bypass on track for April 2027 completion
- This expressway will cause more traffic congestion not only at its junction with Tun Dr....lawrence on Air Itam–Tun Dr LCE Expressway bypass on track for April 2027 completion
- Not enough. Need to drop more... else developer is still pricing arrogantly and way past...Moon on Penang property transactions fall 9.8% in Q3 2026
- ere is no time limit. More importantly, you need to find out whether your type...DAVID CHA CHIN CHYE on New STRA guidelines could see unlicensed listings removed from booking platforms
- The money paid for under tunnel can move to this project? ...ssspring on Penang considers a third bridge Instead of an undersea tunnel
- This headline is not at all reflective of the reality of what has been included...John Camp on Seaside Pocket Park in Tanjong Bungah to proceed with residents’ requests incorporated
- Are u sure this is the resident's design? None of the pictures above showed the...Sussiee on Seaside Pocket Park in Tanjong Bungah to proceed with residents’ requests incorporated
- 1. Which resident’s request was incorporated ? 2. Why was resident not given a chance...Tom on Seaside Pocket Park in Tanjong Bungah to proceed with residents’ requests incorporated
SHOW MORE COMMENTS
Latest Property News