Juru-Sungai Dua Traffic Dispersal Project records 54.61% progress
The first package of the Juru-Sungai Dua Traffic Dispersal Project (PTJSD), valued at RM3 billion, has achieved 54.61% physical progress as of November 8, 2026, marking steady progress in efforts to improve highway capacity and ease congestion along the busy corridor in Penang.
According to a media statement issued by PLUS Malaysia Berhad on November 17, 2026, Package 1 involves improvements to the slip roads at the East-West Interchange Roundabout, as well as the construction of a new bridge at Jalan Tun Hussein Onn.
The works form part of a wider initiative to increase road capacity and improve traffic flow, particularly along the route connecting Juru and Sungai Dua.
Meanwhile, PLUS said Packages 2 to 5 are currently at the final stage of the tender process, with construction works expected to be carried out in stages.
Packages 2 and 5 involve works along the stretches between Juru Toll Plaza and Juru Lay-by, as well as Samagagah Lay-by and Sungai Dua Toll Plaza, respectively.
Packages 3 and 4 will cover the construction of elevated road sections and elevated interchanges between Juru Lay-by and Samagagah Lay-by.
The overall PTJSD project spans 17.4km, connecting Juru Toll Plaza to Sungai Dua Toll Plaza. Once fully completed, it is expected to increase highway capacity, improve traffic flow and provide long-term benefits to highway users and surrounding communities.