AIR ITAM BYPASS
Air Itam–Tun Dr LCE Expressway bypass on track for April 2027 completion
The RM851 million Air Itam–Tun Dr Lim Chong Eu Expressway bypass project is expected to be completed by April 2027, with construction reaching 93.19% progress as of 30 September 2026. Penang Chief Minister Chow Kon Yeow gave the assurance during a site visit in Gelugor, saying the contractor, Consortium Zenith Construction Sdn ... Read More
Ayer Itam bypass reaches 93% completion
The Ayer Itam–Tun Dr Lim Chong Eu Expressway bypass has reached 93% completion, with the remaining works targeted for completion by April 2027. Paya Terubong assemblyman Wong Hon Wai said the project team recently held its 60th monthly progress meeting, which he has been attending since he was elected in ... Read More
Air Itam–Tun Dr LCE bypass reaches 91% completion, on track for April 2027
The construction of the long-awaited bypass road linking Air Itam to Tun Dr Lim Chong Eu Expressway has reached 91% completion, with major structural works continuing to progress on schedule. According to Paya Terubong assemblyman Wong Hon Wai, all bridge beams on the Bandar Baru Air Itam side have been successfully installed. Construction ... Read More
Paya Terubong rep flags slow progress at Air Itam bypass construction
Paya Terubong State Assemblyman Wong Hon Wai has flagged a disparity in construction progress along the new Air Itam–Tun Dr. Lim Chong Eu bypass, following a recent site visit to the elevated highway linking Farlim to Lebuh Tun Lim Chong Eu. Wong, who has been monitoring the project closely, noted that ... Read More
Full road closure at Jalan Thean Teik-Jalan Angsana junction for bypass works
A full road closure from all directions will be implemented at the Jalan Thean Teik-Jalan Angsana junction in phases to facilitate critical beam launching works for the ongoing Air Itam-Lim Chong Eu Expressway bypass project. State Tourism and Creative Economy Committee chairman Wong Hon Wai said the temporary closure is ... Read More
Air Itam–Tun Dr LCE bypass completion pushed to April 2027 following 2nd time extension
The completion date for the second package of the Air Itam–Tun Dr Lim Chong Eu Expressway (LCE) bypass has been pushed from next year to April 12, 2027, following the approval of a second extension of time (EOT). According to Guang Ming Daily, Penang Infrastructure Corporation (PIC) confirmed that the ... Read More
Air Itam–Tun Dr LCE Expressway project reaches 80% completion
The construction of the Air Itam to Tun Dr. Lim Chong Eu Expressway (Package 2), has reached 80% completion and is now entering its critical phase. State Executive Councillor for Tourism and Creative Economy, Wong Hon Wai, announced that a permanent closure of the Lintang Angsana junction will take effect ... Read More
Air Itam-Tun Dr LCE Expressway bypass progressing ahead of schedule
The long-awaited Package Two bypass road, linking Bandar Baru Air Itam to the Tun Dr Lim Chong Eu Expressway, is progressing ahead of schedule, marking a significant step towards alleviating traffic congestion in Penang. State Infrastructure, Transport, and Digital Committee chairman Zairil Khir Johari announced that the project had reached ... Read More
Steady progress on Air Itam bypass construction
Construction of the Air Itam bypass highway is progressing well, with several key milestones achieved. A recent site visit by YB Wong Hon Wai revealed that the piling work for the section between Lebuhraya Thean Teik and Farlim Market has been fully completed. Additionally, reinforced concrete piling for the monsoon ... Read More
Stop-work order issued for Air Itam-Tun Dr LCE Expressway bypass construction
The contractor for the Air Itam-Tun Dr Lim Chong Eu Expressway bypass (Package Two) has been hit with a stop-work order. The Penang Island City Council (MBPP) issued the order to Consortium Zenith Construction (CZC) Sdn Bhd due to non-compliance with established guidelines, as reported by The Star newspaper. Penang ... Read More
Weekly Newsletter
Latest Projects
TODAY'S MOST READ
RECENT COMMENTS
- @santokh This is way better then city of dream! the new landmark of penang island...LL on SITE PROGRESS: The Pier (Nov 2026)
- Need some suggestion please. Is The Terraces or The Cube a good choice to buy?...SG on The Cube
- @santokh We shouldn't say cheap. It's a good addition to Bayan mutiara area. The design...Bin on SITE PROGRESS: The Pier (Nov 2026)
- my gosh! why does it look so "cheap"?? ...santokh on SITE PROGRESS: The Pier (Nov 2026)
- @lawrence The flying over currently build near the TNB is the U turn for traffic...Bin on Air Itam–Tun Dr LCE Expressway bypass on track for April 2027 completion
- This expressway will cause more traffic congestion not only at its junction with Tun Dr....lawrence on Air Itam–Tun Dr LCE Expressway bypass on track for April 2027 completion
- Not enough. Need to drop more... else developer is still pricing arrogantly and way past...Moon on Penang property transactions fall 9.8% in Q3 2026
- ere is no time limit. More importantly, you need to find out whether your type...DAVID CHA CHIN CHYE on New STRA guidelines could see unlicensed listings removed from booking platforms
- The money paid for under tunnel can move to this project? ...ssspring on Penang considers a third bridge Instead of an undersea tunnel
- This headline is not at all reflective of the reality of what has been included...John Camp on Seaside Pocket Park in Tanjong Bungah to proceed with residents’ requests incorporated
SHOW MORE COMMENTS
Latest Property News